House construction

Thumb Rules for house construction 2024

1. Thumb Rule for Concrete Volume

The volume of concrete required = 0.038 m3/square feet area

Example:- If Plan Area = 40 x 20 = 800 Sq. m.

So, for the plan area of 800 Sq. m. the area the total volume of concrete required.

800 x 0.038m3 = 30.4m3

2. Thumb Rule for Steel Quantity for Slab, Beams, Footings & Columns

Following are some important thumb rules for steel calculation for slab, beam, column, and footings.

Steel required in residential buildings = 4.5 Kgs – 4.75 Kgs / sq. Ft.

Steel required For Commercial buildings = 5.0 Kgs-5.50 Kgs/Sq. Ft.

3. Percentage of Steel in Structural Members

Following are thumb rules for reinforcement in concrete members,

1) Slab – 1% of the total volume of concrete (Slab steel calculation thumb rule)
2) Beam – 2% of the total volume of concrete
3) Column – 2.5% of total volume of concrete
4) Footings – 0.8% of the total volume of concrete

Example:

How to calculate the steel quantity of slab having the Length, width, and depth of the slab is 5m x 4m x 0.15m

Step 1: Calculate the Volume of Concrete:

The Total Volume of Concrete for the given Slab = 5 x 4 x 0.15

= 3m3

Step 2: Calculate The Steel Quantity Using the Formula:

As per the guidelines given in the BN Dutta reference book the steel quantity of the slab is 1% of the total volume of concrete utilized.

A thumb rule to estimate the Steel quantity of the above slab = Volume of Concrete x Density of Steel x % of Steel of the Member

Steel weight required for above slab = 3 x 7850 x 0.01 = 235Kgs

4. Thumb Rules For Shuttering Work

Shuttering costs are taken as 15-18% of the total construction of the building. Shuttering work is done to bring the concrete into Shape. The Thumb rule to estimate the shuttering required is 6 times the quantity of concrete or 2.4 times the Plinth area.

For example, if the concrete quantity is 0.5m3, then

Area of Shuttering is 0.5 x 6 = 3m2

Components of Shuttering

Shuttering Ply Quantity estimation

The Shuttering plate Ply, Battens, and Nails are components of Shuttering.

Suppose, The Shuttering Ply has a length, width & depth of 2.44 x 1.22 x 0.012

The No. of Shuttering Ply Sheets = 0.22 times of Shuttering

Suppose, the Shuttering Area = 3m

Then Ply required for shuttering = 0.22 x 3 = 0.66m2

5. Battens Quantity Calculation

Shuttering Batten usually has a length & width of 75mm x 40mm.

Batten Quantity = 19.82 x No. of Ply Sheets

If work requires 25 Ply sheets, the total quantity of Battens is 19.82 x 25 = 495 Battens

Nails & Binding Wire Quantity in Shuttering:

Approximately, 75 grams of Nails were used in the shuttering of the 1m2 area.

75gms of Binding wire is used for every 1m2 of Shuttering.

The thumb rule for Shuttering oil estimation :

Shuttering oil is applied on the shuttering plate surface used to de-frame or de-assemble from the concrete easily.

Total required Shuttering oil  = 0.065 x Total Area of Shuttering

(or)

For every 15m2 of shuttering 1 liter of shuttering oil is consumed.

Example :

If, total area of shuttering is 15 m2, then Shuttering oil Consumption = 0.065 x 15 = 0.975.

6. Thumb Rule for Cement, Sand, Coarse Aggregate Quantity Calculations

Note: 1 bag of cement = 50Kgs

Thumb rule for Cement required in Brickwork, Cement Masonry & Plastering work in construction

7. Thumb Rules For Civil Engineers for Brickwork

The following are Thumb Rules for civil engineering for brickwork and cement quantity calculations.

Brickwork for 1m3Cement Qty in m3Cement Qty in Bags
230 mm Brickwork0.876m325.4 Bags
115 mm Brickwork0.218m36.32 Bags

8. Thumb Rules For Cement Masonry Quantity

Cement Masonry Type & MixCement Qty in BagsCement Qty in Kgs
200mm in Cement Masonry work
of Ratio 1:6
0.124Bags/m26.2Kgs/m2
150mm in Cement Masonry work
of Ratio 1:6
0.093Bags/m24.65Kgs/m2
200mm in Cement Masonry work
of Ratio 1:4
0.206Bags/m210.3Kgs/m2
150mm in Cement Masonry work
of Ratio 1:4
0.144Bags/m27.2Kgs/m2
100mm in Cement Masonry work
of Ratio 1:4
0.103Bags/m25.15Kgs/m2

8. Thumb Rules Plastering Quantity

Type of PlasteringCement Qty in BagsCement Qty in Kgs
Rough Plastering0.09 Bags/m24. 5Kgs/m2
Internal Wall Plastering0.09 Bags/m24.5 Kgs/m2
Duct Plastering0.09 Bags/m24.5 Kgs/m2
External Wall plastering0.175 Bags/m28.75 Kgs/m2
Stucco Plastering0.175 Bags/m28.75 Kgs/m2
Lathen Plastering0.55 Bags/m227.5 Kgs/m2

9. Thumb Rules In Building Construction Cost

The thumb rule for house construction cost is a rough estimation of the total cost of construction based on the built-up area of the house. Typically, thumb rules are quick and easy to use but are not precise and may not take into account specific factors that affect the actual cost of construction.

As an approximate guide, a common thumb rule for house construction cost is between Rs. 1500 to Rs. 2500 per square foot, depending on factors such as the quality of materials used, location, design, and labour costs. This would mean that a 1000 square feet house may cost between Rs. 15 lakhs to Rs. 25 lakhs.

Below is a general thumb rule that can be used to estimate the building materials and work required for a given unit area of construction.

Sr. No.Material/ WorkThumb Rule
1.Cement (bags)0.43 bags / sq ft
2.Sand (cu.ft)2.5 kg / sq ft
3.Aggregate (cu.ft)1.20 cu ft / sq ft
4.Steel (kg)1.34 cu ft / sq ft
5.Bricks (Nos.)7.3 no / sq ft
6.Tiles (Nos.)0.7 nos / sq ft
7.Colour (Liters)0.12 lit / sq ft
8.Finishing Works₹ 470/sq ft
9.Electrical Cost₹ 250 /sq ft
10.Plumbing Cost₹ 150 /sq ft
11.Fire Fighting Cost₹ 45 /sq ft
12.Exterior Cost₹ 94.5 / sq ft

Thumb Rule according to materials percentages,

DescriptionThumb rule (% of Total Cost)
Cement14.4%
Sand12.3%
Aggregate7.4%
Steel20.6%
Painting material5.1%
Tiles8%
Bricks5.4%
Window3%
Doors4.4%
Plumbing7.5%
Electrical6.8%
Sanitary4.1%

Thumb Rules For Construction Cost

The cost of construction can vary depending on the quality of materials and workmanship used. Below is an overview of the average construction costs based on the quality of construction. This information can serve as a useful reference point for estimating the costs of a building project.

Sr. No.Construction based on QualityThumb Rule
1.Basic Quality Construction1000 Rs./Sqft
2.Medium Quality Construction1300 Rs./Sqft
3.High Quality Construction1700 Rs./Sqft

1000 Sqft House Average Cost Of Construction Thumb Rule

Sr. No.Description of Work1000 sq ft House Average Cost
1.Architectural CostRs. 12,500 Onwards
2.Brick wall Construction without RCCRs. 700 per sqft
3.Brick wall Construction With RCCRs. 850 per sqft
4.Civil Construction WorkRs. 1400 per sqft
5.Electric and Plumbing WorkRs. 2400 per sqft
6.Raw Material Cost In ConstructionRs. 8 Lakh Onwards

A common approach to estimating building costs is to use a thumb rule based on the percentage of the total project cost. This method provides a rough estimate of the building cost and is often used as a starting point for budgeting purposes.

Sr. No.WorkCost
1.Excavation and Filling Earthwork0.6%
2.Foundation Work4.9%
3.DPC1.2%
4.Brick work32%
5.Roofing22%
6.Flooring5%
7.Doors and window17%
8.Plastering9%
9.White Washing3%
10.Miscellaneous5.5%

Leave a Reply

Your email address will not be published. Required fields are marked *