Building construction thumb rule |shuttering & Productivity
Thumb rules help you in finding out the solution within a minute using a simple formula and make smart decisions whenever needed. But, while using these thumb rules, you must remember that the thumb rule never gives the exact or accurate results, you just have used them for approximate Values
Labour Productivity thumb rule
Brick :- 1.5 Sq mt
1 mason , 1 Men Helper and 1 Women Helper
Block work (200 mm) :- 12 sq mt
1 mason , 1 Men Helper and 1 Women Helper
Wall Plastering :-1.12 Sq mt
1 mason , 1 Men Helper and 1 Women Helper
External Plastering:-7.85 sq mt
1 mason , 1 Men Helper and 1 Women Helper
Ceiling Plastering :- 7 sq mt
1 mason , 1 Men Helper and 1 Women Helper
Shuttering :- 5 Sq mt
1 Carpenter 1 Unskilled
Steel binding :- 250 kg
1 Fitter 1 Helper
Tile work :- 12 sq mt
1 Mason 1 Helper
Plastering Quantity :
Type of Plastering | Cement Qty in Bags | Cement Qty in Kgs |
Rough Plastering | 0.09 Bags/m2 | 4. 5 Kgs/m2 |
Internal Wall Plastering | 0.09 Bags/m2 | 4 Kgs/m2 |
Duct Plastering | 0.09 Bags/m2 | 4.5 Kgs/m2 |
External Wall plastering | 0.175 Bags/m2 | 8.75 Kgs/m2 |
Stucco Plastering | 0.175 Bags/m2 | 8.75 Kgs/m2 |
Lathen Plastering | 0.55 Bags/m2 | 27.5 Kgs/m2 |
Percentage of Steel in Structural Members :
- Slab – .8 to 1 % of the total volume of concrete
- Beam – 2% of the total volume of concrete
- Column – 2.5 to 3 % of total volume of concrete
- Footings – 0.8 to 1.5 % of the total volume of concrete
Concrete:
Commercial Building :- 0.5 A m3
Residential Building :- 0.2 A m3
A= Total Built Up Area. (i.e. Plinth Area x No. of Floor)
Steel:
Residential Building :- 4.5-4.75 kg per Sq ft of Built up Area
Commercial Building :- 5.0-5.5 kg per Sq ft of Built up Area
Thumb Rules for Shuttering area:
Thumb rule to estimate the shuttering required is 6 times the quantity of concrete or 2.4 times of Plinth area.
For example, the concrete quantity is 15 m3, then
Area of Shuttering is 15 x 6 = 90 m2
Shuttering Ply Quantity :-
Shuttering Ply has a length, width & depth of 2.44 x 1.22 x 0.012
No. of Shuttering Ply sheets = 0.22 times of Shuttering
Shuttering area = 90 m
Then Ply required for shuttering = 0.22 x = 19.8
Batten Quantity
Shuttering batten usually have a length & width of 75mm x 40mm.
Batten Quantity = 19.82 x No. of Ply Sheets
If work requires 20 Ply sheets, the total quantity of Battens are 19.82 x 20 = 396.4 Battens
Nails & Binding Wire
Approximately, 70 gm of Nails used in shuttering of 1m 2 area.
70 gm of Binding wire is used for every 1m2 of Shuttering.
Shuttering oil
Shuttering oil is apply on shuttering plate surface used to de-frame or de-assemble from the concrete easily.
Total required Shuttering oil = 0.065 x Total Area of Shuttering
If, total area of shuttering is 15 m2, then Shuttering oil Consumption = 0.065 x 90 = 6 litre.